Thursday, May 6, 2010

Termimesh...



All the termimesh is in. No termite issues for me. I learned that most all termite infestations happen at the pipe penetrations in the slab. Not at this house.

Island...



Electrical for the island.

Wednesday, May 5, 2010

Almost done...



With the rebar on the house. They still have some work to do. I'm waiting on the electrician and termimesh people right now. Then they need to get the negiotated steps ready. They plan to pour the slab tomorrow. Only after it passes inspection.

More work...



Rebar & plumbing for casita.

Monday, May 3, 2010

Plumbers...



Are doing the rough in today. Back on track.

Sunday, May 2, 2010

Another picture...



This is the casita.

Digging deeper...



They had to dig the outside footers deeper than originally done. There have been some challenges already and we have been working through them. Our timeline seems to be off by a couple of days now. Our estimated pour date is next friday instead of wednesday. The plumbers will be out on monday. Good times.

Friday, April 30, 2010

Forms are going up...



Today they should be finished with them. Tomorrow the plumbing crew should be out.

Monday, April 26, 2010

It is happening...



Yes ladies and gentlemen...it is happening. They have already put up the markers and have started to do some clearing. They said that in 1.5 weeks we should be ready to pour. It is very surreal.

Thursday, April 22, 2010

Now we are there...

After a long time...it's starting. We had our meeting with our consultant this morning. I had to breathe...I almost forgot. It's a lot to take in. About an hour later I felt better and ready to go. I met with a concrete guy today...and he is going to start doing the site prep starting Monday. Yes, it is really happening. I'm excited, nervous and all other kinds of things.

Now...to the management of subcontractors, budgets, deadlines, paperwork and my own sanity.

Until the next update, HAPPY EARTH DAY!!!