Friday, May 28, 2010

Sneaky little guy...



Wanted to blend in with the framing. Almost missed the stick bug. It had pretty green markings.

Kitchen...



Area of the house. Another look at the unpainted siding. Looks like it is on schedule to be painted next Tuesday.

Wednesday, May 26, 2010

Board and batten...



Siding on the casita. I'm looking forward to seeing it painted.

Woohoo...



I finally have all the ceiling fans...7 of them. Glad that choice is over. Now to pick some kitchen lights. Choices..pendant, track or sconce lighting?

Finally cleaned...



The "curbed" areas on the slab are dried and cleaned. Had to get a wet/dry vac to get the job done. I did notice today that the curbed area in the casita doesn't have a drain. Missed during the rough-in plumbing. I'm looking into my options with this situation. As with any house...there are challenges always being presented. So far...i've had my share already.

Registers...



Are being placed in the house. Here are the ones in the living room.

The A/C is...



Delivered. It is in the shed for now. Being in Texas, this is one of the most important parts of a house. I'm excited about this going in the house. I believe they are doing a good job. I hope it stays that way.

Working hard...



On the casita.

Monday, May 24, 2010

Siding sample...



This is a small sample of the board and batten style siding. They have a lot more to put up. It looks really good so far.

Sunday, May 23, 2010

Get ready...



To visit. We have a petting zoo. Just don't feed the bears. We think this a water snake based on pictures we looked at in a native Texas snake brochure. It was hiding under a pile of lumber in a wet spot. It was happy until we messed with it. It went and hid under some other lumber. It was more scared of us. Ready to come visit?

Saturday, May 22, 2010

Window seat...



Windows are now at a good height.

Friday, May 21, 2010

The master...



Bedroom.

Changes...



After seeing the windows in we noticed some flaws in the plans. "When momma isn't happy, ain't nobody happy" The window seat and lower kitchen windows are too high. Can't see out of the window seats while sitting and can't see out of the kitchen windows unless extremely tall or on a small ladder. Those are getting fixed. Also, you can see the pocket door frames.

Windows...



Are starting to go in. However, they forgot to send the casita windows. So, they can't start all the siding yet. They will start siding on the house tomorrow. Also, the roof decking is up on the house, but we need more roof decking for the casita. Next week we should be getting the rest of the materials and send the surplus back. It has been quite a journey while finishing up week four.

Wednesday, May 19, 2010

In the living room...



Looking at the dining/kitchen area.

Front door...



And front porch area. It is starting to look more like a house. The windows are being delivered on friday. I'm sure by then i could imagine it really looking like a house. Most of the area is dry enough to work. There is still some water in the "curbed" areas of the slab. I've been trying to empty the water in the casita one. Takes time with a cup and a bucket.

Fiberboard...



Is going up around the kitchen area.

Casita...



Front porch looking at front of the main house.

Not wasting...



Any time!

Tuesday, May 18, 2010

Casita roof...



Yes, it is happening. Everything is looking good. I'm excited to see what happens next.

Sun...hurry!



We gotta dry this place out! Another rain came through last night. The crew just arrived and starting to get busy. We need more lumber, but have too much of other lumber that needs to be sent back. Today we should be getting the roof decking, wall sheathing, cornice, etc.  Good Times!

It's where...?



Yes, that is where the fireplace and window seats will go. Good luck figuring out where it is. There are bracing boards everywhere!

Saturday, May 15, 2010

The roof...



Is already forming. Trusses, engineered beams, rafters...oh my!

Casita framing...



It is muddy...but, it is happening.

Yikes...



Had a heavy rain and there are lots of puddles on the slab.

Wednesday, May 12, 2010

Interior walls...



Are going up in the house now.

Framing...



Has started!

Monday, May 10, 2010

House slab...



Done.

Casita slab...



Done.

Thursday, May 6, 2010

Casita poured...



Almost there.  Just details now. Last concrete truck is gone. Pump truck is leaving. They should be back tomorrow to take the form boards off and clean up.

Working on the...



Front porch.

About 75% there...



Most of the house is poured. Just the minor details and the porch are what is left to pour. The casita still needs to get poured.

Starting to see...



A real slab.  Look forward to seeing it completed.

More concrete...



This is the area where the fireplace will be located.

It is going in...



We are on concrete truck #2.

First concrete truck...



It is about to start.

Termimesh...



All the termimesh is in. No termite issues for me. I learned that most all termite infestations happen at the pipe penetrations in the slab. Not at this house.

Island...



Electrical for the island.

Wednesday, May 5, 2010

Almost done...



With the rebar on the house. They still have some work to do. I'm waiting on the electrician and termimesh people right now. Then they need to get the negiotated steps ready. They plan to pour the slab tomorrow. Only after it passes inspection.

More work...



Rebar & plumbing for casita.

Monday, May 3, 2010

Plumbers...



Are doing the rough in today. Back on track.

Sunday, May 2, 2010

Another picture...



This is the casita.

Digging deeper...



They had to dig the outside footers deeper than originally done. There have been some challenges already and we have been working through them. Our timeline seems to be off by a couple of days now. Our estimated pour date is next friday instead of wednesday. The plumbers will be out on monday. Good times.