Thursday, May 6, 2010

Working on the...



Front porch.

About 75% there...



Most of the house is poured. Just the minor details and the porch are what is left to pour. The casita still needs to get poured.

Starting to see...



A real slab.  Look forward to seeing it completed.

More concrete...



This is the area where the fireplace will be located.

It is going in...



We are on concrete truck #2.

First concrete truck...



It is about to start.

Termimesh...



All the termimesh is in. No termite issues for me. I learned that most all termite infestations happen at the pipe penetrations in the slab. Not at this house.

Island...



Electrical for the island.

Wednesday, May 5, 2010

Almost done...



With the rebar on the house. They still have some work to do. I'm waiting on the electrician and termimesh people right now. Then they need to get the negiotated steps ready. They plan to pour the slab tomorrow. Only after it passes inspection.

More work...



Rebar & plumbing for casita.